Additional Costs in Sub-Rent Contracts
You can define and add additional costs for sub-rent contracts. This chapter is divided into the following sections:
- Setting up Additional Cost Centers for Sub-Rent Contracts
- Adding Additional Costs to a Sub-Rent Contract
Setting up Additional Cost Centers for Sub-Rent Contracts
You can define and add additional costs for sub-rent contracts.
To do so, please proceed as follows:
- Use the quick search (ALT+Q) to find the Contract Additional Cost Setup page.
- The Contract Additional Cost Setup page is displayed.
- Select New > New from the menu bar.
Note
You can also create an additional cost line from an additional contract revenue. To do so, click on New > New from Add. Revenue. For more information on creating additional revenues, click here.
- Now enter the desired settings for your additional cost center.
You can choose between the following options:
| Option | Description |
|---|---|
| Active | Specifies whether the additional cost line is active. |
| Standard Description | Specifies the default description for the additional cost line. This field will be displayed in the contract line. |
| Requirement | Specifies whether the additional cost line is necessary, optional or recommended for a contract. |
| Unit Of Measure Code (On Registration) | Specifies the unit of measure with which the line is invoiced in case the price type is set to Once or On Registration. |
| Price Type | Specifies the price type of the additional cost line. |
| Cost Item No. | Specifies the cost item number which is used for invoicing the additional costs. |
| Price Base | Specifies the price base for the Price Type Recurring. |
| Standard Invoice Calendar | Specifies the days to be invoiced. If this field is not filled, all days will be invoiced. |
- Your settings are saved automatically.
- Close the Contract Additional Cost Setup page.
You have successfully defined an additional cost center.
Adding Additional Costs to a Sub-Rent Contract
To add the set up additional cost center to a sub-rent contract, please proceed as follows:
- Use the quick search (ALT+Q) to find the Sub-Rent Contracts page.
- The Sub-Rent Contracts page is displayed.
- Select the desired sub-rent contract or create a new sub-rent contract.
- In the menu bar of the Lines FastTab, click on Functions > Add General Additional Costs.
- The Select Additional Costs page is displayed.
- Click on the desired additional cost center.
- Click on Edit List in the menu bar.
- Enter the desired price into the Unit Cost field.
- Click OK to confirm your selection.